Dewatering AHA Example for Construction — Free EM 385 Template

Free dewatering and cofferdam AHA example for USACE/NAVFAC work — EM 385-1-1 (2024) citations, job steps, hazards, controls, and residual RACs.

Download Word Sample (free) Download PDF Sample (free)
Free download, no email required. Adapt every step, hazard and control to your site's actual conditions before your SSHO signs it.
On a phone? Tap the PDF to view it, then use the share icon to text or email it — the Word file is best opened on a computer.

Dewatering and cofferdam operations cover the temporary control of surface water and groundwater so excavation, foundation, and marine structure work can proceed in the dry: sump and wellpoint pumping, sheet-pile or portable cofferdam installation, discharge management, and controlled removal. There is no dedicated dewatering chapter in EM 385-1-1 (15 March 2024), so this activity hazard analysis is a composite: Chapter 25 (Excavation and Trenching) governs protection from water (25-8.c), cofferdams (25-8.k), and the Controlled Flooding Plan (25-7.h); Chapter 11 governs pump power and GFCI protection; and Chapter 19 applies when work is performed from floating plant. On the OSHA side, 29 CFR 1926.651(h) covers water accumulation in excavations and 29 CFR 1926.802 covers cofferdams.

This AHA example is written for contractors on USACE and NAVFAC contracts — the SSHO who has to get the AHA accepted before the preparatory meeting, and the project engineer assembling the Excavation and Trenching Plan submittal that must accompany it. Because dewatering supports a larger definable feature of work, expect the government to ask how this AHA interfaces with your excavation AHA, your temporary power AHA, and — for cofferdams near navigable water — your Controlled Flooding Plan and vessel protection measures.

The template below follows ENG Form 6206 (SEP 2024): sequenced job steps with hazards, controls written to the hierarchy in para 2-6.b, a residual Risk Assessment Code for each step, and the supporting equipment, training, inspection, and competent person entries with chapter-paragraph citations you can verify against the manual. One edition note before you copy anything: solicitations issued on or after 15 March 2024 fall under the 2024 edition and its chapter-paragraph citation style, while contracts awarded under the 2014 edition keep the old 01.A-style numbering until completion — this AHA example cites the 2024 edition.

Risk Assessment Code (RAC) Matrix — EM 385-1-1 (2024)

Severity ↓ / Probability →FrequentLikelyOccasionalSeldomUnlikely
CatastrophicEEHHM
CriticalEHHML
ModerateHMMLL
NegligibleMLLLL

E = Extremely High Risk · H = High Risk · M = Medium Risk · L = Low Risk (per EM 385-1-1 2024, para 2-2.u/2-2.w and ENG Form 6206). Controls must reduce the residual RAC to a level the approval authority accepts before work proceeds.

Sample AHA: Dewatering and Cofferdam Operations

On a phone, swipe the table sideways to see the controls and residual RAC columns →

Overall RAC: M — Medium Risk (highest residual step RAC, per EM 385-1-1 2024 para 2-6.d(4)(f))

Job StepHazardsControls (hierarchy: elimination → engineering → administrative → PPE)Residual RAC
Mobilization, utility locates, and plan submittalsStriking underground utilities while installing wellpoints, sumps, or driving cofferdam sheeting
  • Obtain dig permits and locate and mark all underground utilities, then physically verify by hand digging or vacuum excavation within 3 ft of the marked location before any mechanical excavation or sheet driving (25-8.f).
  • Review as-builts and utility owner records with the Competent Person, Excavation before finalizing wellpoint and sheet-pile layout.
  • Treat unverified marked utilities as energized and reroute wellpoint or sump locations rather than working blind over a marked line.
L
Starting work without accepted plans and AHA — uncontrolled hazards during first drawdown
  • Submit the Excavation and Trenching Plan, developed by the CP, for any excavation 5 ft or deeper and obtain USACE/KO acceptance before beginning work (25-7).
  • For cofferdams, include a Controlled Flooding Plan covering fall protection, access and egress, and evacuation procedures (25-7.h).
  • Have every involved employee review and sign this AHA before starting, and hold the preparatory meeting with the AHA already accepted (2-6.d(2), 2-6.d(4)(h)).
L
Set up temporary power, generators, and pump electricalElectrocution from pump circuits, cords, and connections in a wet environment
  • Provide GFCI protection on all 125-volt, 15-, 20-, and 30-amp and greater receptacles supplying temporary power, and on all circuits serving portable tools and pumps (11-8.l(9)).
  • Use only submersible pumps designed by the manufacturer for wet locations; a Qualified Person must install and test each pump (11-8.m(6)).
  • Where personnel are or could be in the water during pump operation, equip the pump with a UL 943 Class A GFCI; if the manufacturer prohibits personnel in the water, implement a Hazardous Energy Control Program with LOTO instead (11-8.m(6)).
  • Bond the neutral to the generator frame and provide GFCI protection on portable and vehicle-mounted generators (11-8.l(1), NFPA 70 445.20(B) and 590.6(A)(3)).
  • Test all GFCIs monthly, and test portable GFCIs for designed functionality before each use (11-5.e, 11-8.m(2)).
L
Cords and discharge hoses creating trip hazards and mechanical damage to conductors
  • Elevate or route cords and hoses out of walkways, access ramps, and equipment travel paths.
  • Protect cords passing through work areas from damage and remove damaged cords from service immediately.
L
Install cofferdam sheeting or wellpoint systemDrowning — personnel working on or over water during sheet driving
  • Provide inherently buoyant Type III or Type V work vests or better USCG-approved PFDs, properly worn, for all personnel on structures or equipment over or next to water without guardrails (5-8.g).
  • Stage ring buoys with at least 90 ft of 3/8-inch line at intervals not exceeding 200 ft along the waterfront work area (5-8.g).
  • Provide a lifesaving skiff with trained launch and operating personnel immediately available where a drowning hazard exists (5-8.l, 5-3.e).
  • If work is performed from barges or work boats, inspect the floating plant before use and operate it with trained motorboat operators (19-5.a(4), 19-3.b).
M
Struck-by during handling and driving of sheet piles
  • Rig and handle sheets under a designated rigger with tag lines; keep all personnel clear of suspended sheets and the hammer fall zone.
  • Establish exclusion zones around the crane and driving template and enforce them with physical barriers or a spotter.
  • Coordinate this step with your pile driving AHA where a pile rig is used (Ch 16).
L
Falls from the cofferdam top or template into the excavation or water
  • Provide standard guardrails or equivalent Chapter 21 protection wherever personnel or equipment are required or permitted on the cofferdam (25-8.k(2)).
  • Provide walkways, bridges, or ramps with at least two means of rapid exit, each equipped with standard guardrails (25-8.k(3)).
L
Initial drawdown and pumping operationsCofferdam overtopping or failure during drawdown
  • Where overtopping by high water is possible, the cofferdam design must include provisions for controlled flooding of the work area (25-8.k(1)).
  • An RPE must plan and direct all pumping, drainage, freezing, or similar groundwater control measures, addressing moisture balance in surrounding soils and effects on adjacent foundations (25-8.c).
  • Develop, post, and brief evacuation procedures with distinct warning signals for emergency evacuation and for controlled flooding (25-8.k(4)).
  • Draw down in staged lifts while the CP monitors sheeting deflection, seepage, and boil formation at the base.
M
Pump or power failure allowing rapid water accumulation
  • Provide an emergency power source wherever continuous operation of groundwater control equipment is necessary (25-8.c).
  • The CP must monitor water control equipment and operations to ensure proper operation (25-8.c, 1926.651(h)(2)).
  • Maintain standby pumps of equal capacity, staged and plumbed, and establish a water-level trigger for stopping in-excavation work.
L
Excavation and construction work inside the dewatered areaCave-in of excavation faces destabilized by seepage or drawdown
  • Do not permit work in excavations where water is accumulated or accumulating unless the water hazard is controlled (25-8.c, 1926.651(h)(1)).
  • The CP must conduct documented inspections before each shift, throughout the shift, after every rainstorm, and whenever seepage, fissures, sloughing, or bottom bulging occur (25-5.a).
  • Classify soil at the start of each shift and as conditions change, and document results for the life of the project (25-5.b).
  • Use the sloping, benching, or protective systems required by the accepted Excavation and Trenching Plan (25-7, Ch 25).
L
Hazardous atmosphere in deep, dewatered excavations
  • In excavations 4 ft or deeper where oxygen deficiency or gaseous conditions are known or suspected, test the air before each shift or more often as directed by the CP, and log all results at the work site (25-5.c).
  • Ventilate or evacuate and re-test whenever readings exceed action levels; evaluate confined space applicability for cofferdam cells (Ch 34).
L
Blocked emergency egress from the cofferdam or excavation
  • Maintain both means of rapid exit clear of hoses, materials, and spoil at all times (25-8.k(3)).
  • Verify egress routes and evacuation signals at each shift briefing against the posted procedures (25-8.k(4)).
L
Discharge management and environmental controlsErosion, undermining, or flooding at the discharge point
  • Discharge through energy dissipaters or onto stabilized surfaces located away from excavation edges, slopes, and cofferdam toes.
  • Use diversion ditches, dikes, or other means to keep surface water and returned discharge from re-entering the excavation (25-8.c).
  • Walk the full discharge line each shift to check for leaks, hose failure, and ponding against structures.
L
Sediment-laden discharge violating water quality permits
  • Route discharge through the sediment controls (bags, basins, tanks) required by the project permit before release.
  • Monitor turbidity or discharge clarity at the frequency the permit requires and stop pumping if controls are overwhelmed.
L
High-water events and controlled flooding contingencyRising water overtopping the cofferdam and trapping personnel or equipment
  • Monitor weather forecasts and river/tide gauges against the trigger elevations in the Controlled Flooding Plan and stop work at the defined action stage (25-7.h).
  • Sound the posted warning signal and evacuate personnel and equipment by the designated rapid egress routes before initiating controlled flooding (25-8.k(3), 25-8.k(4)).
  • Flood the work area in a controlled manner per the design to equalize pressure rather than allowing sudden overtopping (25-8.k(1)).
  • Drill the evacuation procedure with all crews before first drawdown and after crew changes.
M
Vessel strike against a cofferdam near a navigable channel
  • Protect cofferdams located close to navigable shipping channels from vessels in transit — fendering, warning buoys, lighting, and notice to mariners as required (25-8.k(5), 1926.802(c)).
  • Coordinate marine traffic notifications with the USCG and the district as required by the contract.
L
System removal, rewatering, and demobilizationUncontrolled rewatering or ground movement during sheet extraction
  • Remove protective systems and sheeting in the sequence planned and directed by the RPE, allowing controlled rewatering to equalize head before extraction (25-8.c).
  • Keep personnel out of the excavation once pumping stops and water begins to accumulate (25-8.c, 1926.651(h)).
L
Electrical energy during pump and temporary power removal
  • De-energize, verify, and lock out pump circuits before disconnecting pumps and cords (Ch 12, Ch 11).
  • Have a Qualified Person remove generator connections and temporary wiring.
L
Struck-by during sheet pulling and equipment loadout
  • Maintain exclusion zones under the extraction rig; use tag lines and a spotter for swinging sheets.
  • Inspect rigging before use and stage extracted sheets on stable dunnage away from the excavation edge (25-8.d).
L

Equipment To Be Used

Training Requirements

Inspection Requirements

Competent / Qualified Person Requirements

Applicable EM 385-1-1 (2024) Sections

Applicable OSHA Standards

Need an AHA for a job that's not in the library?

We write a complete, editable Word AHA for your specific job (your "definable feature of work") — EM 385-1-1 (2024) citations, ENG Form 6206 layout, employee sign-off sheet included — delivered by email within 24 hours. $19 per AHA.

Order a Custom AHA — $19 →

How it works: at checkout you fill in a required "Activity / DFOW" field describing your job — that starts the clock. We confirm any details by email and deliver within 24 hours. Need it same-day? Say so in that field — usually possible. If your reviewer doesn't accept the format, we revise it or refund you in full — your call.

See a sample of exactly what you'll receive →

Frequently Asked Questions

What EM 385-1-1 chapter covers dewatering?

There is no dedicated dewatering chapter in the 2024 edition. Dewatering is governed by Chapter 25 (Excavation and Trenching) — chiefly 25-8.c Protection from Water, 25-8.k Cofferdams, and the 25-7.h Controlled Flooding Plan — with Chapter 11 covering pump power and GFCI protection and Chapter 19 applying to work from floating plant.

When do I need a Controlled Flooding Plan?

Whenever your work involves a cofferdam. Para 25-7.h requires the Excavation and Trenching Plan to include a Controlled Flooding Plan covering fall protection, access and egress, and evacuation procedures, and 25-8.k(1) requires the design to include controlled flooding provisions if overtopping by high water is possible. The evacuation procedures and warning signals must be posted at the jobsite (25-8.k(4)).

Do my dewatering pumps need GFCI protection?

Yes. Submersible pumps may only be used in wet locations when designed for that purpose, a Qualified Person must install and test each pump, and when personnel are or could be in the water during operation the pump must have a UL 943 Class A GFCI (11-8.m(6)). All GFCIs must be tested monthly (11-5.e).

What should the overall RAC be for a dewatering AHA?

The overall RAC must not be lower than the highest residual step RAC (2-6.d(4)(f)). For cofferdam dewatering, the drawdown and high-water contingency steps typically carry residual M even after engineering controls, so an overall RAC of M (Medium) is normal. An overall L usually signals the cofferdam failure and drowning hazards were underrated.

Does the 2014 or 2024 edition of EM 385-1-1 apply to my contract?

Solicitations issued on or after 15 March 2024 fall under the 2024 edition; contracts awarded under the 2014 edition remain on it until completion. Check your contract's referenced edition before citing — the 2024 edition uses chapter-paragraph citations (25-8.k), while 2014 citations look like 01.A.14. This page cites the 2024 edition.

Does OSHA Subpart P or Subpart S apply to cofferdam work?

Both. 29 CFR 1926.651(h) (Subpart P) governs water accumulation in the excavation you are dewatering, and 29 CFR 1926.802 (Subpart S) governs the cofferdam itself — controlled flooding provisions, warning signals, guarded walkways, and protection from vessels. EM 385-1-1 layers the written plan, CP, and RPE requirements on top of both.