Pile Driving Activity Hazard Analysis (AHA) Example — Free EM 385-1-1 Template

Free pile driving AHA example per EM 385-1-1 (2024): job steps, hazards, controls, residual RACs, plus the 16-7.e safety plan and inspection requirements.

Download Word Sample (free) Download PDF Sample (free)
Free download, no email required. Adapt every step, hazard and control to your site's actual conditions before your SSHO signs it.
On a phone? Tap the PDF to view it, then use the share icon to text or email it — the Word file is best opened on a computer.

Pile driving is a definable feature of work (DFOW) with some of the highest struck-by and dropped-load exposure on a federal construction site: multi-ton hammers traveling in leads, piles hoisted overhead, pressurized hoses, and rigs working at the edge of their stability envelope — often from a barge. Under EM 385-1-1 (15 March 2024), pile drivers are load handling equipment (LHE) governed by Chapter 16, with pile-specific requirements concentrated in para 16-8.ff, rigging requirements in Chapter 15, and Chapter 19 added whenever the work goes waterborne.

Contractors on USACE and NAVFAC projects must prepare an activity hazard analysis for this DFOW before work begins (para 2-6), and Chapter 16 adds teeth: the AHA must document crane operator certifications, qualifications, and designations (16-6.a), and pile driving may not start until the contractor has developed a site-specific pile driving safety plan covering utilities, assembly/disassembly sequences, a geotechnical report, daily documented equipment inspections, and a controlled work area plan (16-7.e). This AHA example is written for the SSHO or project engineer who has to get that package through government review.

The example below follows the ENG Form 6206 (SEP 2024) structure: sequenced job steps with hazards, controls keyed to verified EM 385-1-1 paragraph numbers, residual Risk Assessment Codes, and the equipment, training, inspection, and competent/qualified person entries reviewers look for. One edition note before you copy anything: solicitations issued on or after 15 March 2024 fall under the 2024 manual cited here, while existing contracts remain on the 2014 edition (with its old 01.A-style numbering) until completion — confirm which edition your contract invokes before you submit.

Risk Assessment Code (RAC) Matrix — EM 385-1-1 (2024)

Severity ↓ / Probability →FrequentLikelyOccasionalSeldomUnlikely
CatastrophicEEHHM
CriticalEHHML
ModerateHMMLL
NegligibleMLLLL

E = Extremely High Risk · H = High Risk · M = Medium Risk · L = Low Risk (per EM 385-1-1 2024, para 2-2.u/2-2.w and ENG Form 6206). Controls must reduce the residual RAC to a level the approval authority accepts before work proceeds.

Sample AHA: Pile Driving Operations

On a phone, swipe the table sideways to see the controls and residual RAC columns →

Overall RAC: M — Medium Risk (highest residual step RAC, per EM 385-1-1 2024 para 2-6.d(4)(f))

Job StepHazardsControls (hierarchy: elimination → engineering → administrative → PPE)Residual RAC
Mobilization, utility locates, and pre-work planningContact with above- or below-grade utilities by the rig, leads, or driven pile
  • Develop the site-specific pile driving safety plan before any driving or extraction begins, identifying the location of all above- and below-grade utilities (16-7.e(1)).
  • Obtain and review a geotechnical report identifying subsurface and surface conditions at each pile location before finalizing rig travel paths and pile layout (16-7.e(5)).
  • Designate specific areas for equipment operations and material storage clear of marked utility corridors and overhead lines (16-7.e(2)).
L
Unauthorized personnel entering the pile driving work zone
  • Implement the controlled work area plan from the 16-7.e safety plan — physical barricades and signage that prevent access by anyone not directly involved in the operation (16-7.e(7)).
  • Notify the KO or COR within 24 hours of any LHE entering the site so government spot checks can occur before operations start (16-5.c).
  • Brief the controlled-area boundaries at the preparatory meeting and have every involved employee review and sign the AHA before starting work (para 2-6.d(2)).
L
Assembly of crane, leads, and hammerStruck-by or crushing injury during assembly/disassembly of pile driving equipment
  • Follow the written assembly and disassembly sequence required in the site-specific pile driving safety plan (16-7.e(3)).
  • Assemble pile driving leads using only the approved fasteners and torque values required by the manufacturer, with leads of adequate size, length, and strength for the hammer, pile, and driving position (16-8.ff(10)(a)).
  • Comply with all manufacturer's instructions and procedures; where none exist, use QP-developed operational procedures and RPE-sealed capacity procedures (16-8.a, 16-8.ff(2)).
M
Structural failure of a modified excavator or forklift pile-driving attachment
  • Have a Registered Professional Engineer design any LHE pile driving attachment used for other than its intended purpose, such as an excavator or forklift modified for pile driving (16-8.ff(3)).
  • Have an RPE seal and sign the procedures related to the capacity of the equipment before use (16-8.ff(2)(b)).
  • Permit only operators trained and authorized on the specific pile driving attachment to run it, with the manufacturer's load rating charts for approved attachments kept onsite (16-8.ff(4), 16-8.ee(2)(d)).
L
Rig tipover or instability during setup
  • Provide guys, outriggers, thrust outs, counter-balances, or rail clamps as necessary to maintain stability of the pile-driver rig (16-8.ff(9)).
  • Verify ground bearing capacity against the geotechnical report and prepare mats or pads at each setup location before positioning the rig (16-7.e(5)).
M
Rigging and hoisting piles into the leadsDropped pile from rigging failure or accidental disengagement
  • Have a Qualified Rigger inspect all rigging and rigging hardware before use each shift and as necessary during use, per manufacturer's instructions and ASME B30 (15-5.a).
  • Perform all pile hoisting and driving using a closed shackle or other positive attachment that prevents accidental disengagement of the rigging (16-8.ff(15)(b)).
  • Keep all employees clear of piling being hoisted into the leads (16-8.ff(15)(a)).
M
Struck-by from a swinging or rotating pile during hoisting
  • Use taglines to control unguided piles and free-hanging (flying) hammers (16-8.ff(15)(c)).
  • Use a qualified signal person to direct the operator whenever the load or landing area is not in the operator's full view (29 CFR 1926 Subpart CC).
  • Restrict the hoisting path to the controlled work area established under 16-7.e(7).
L
Driving piles (impact or vibratory hammer)Hammer disengages from the leads and falls or rises uncontrolled
  • Equip the pile driver with positive and negative restraint devices to prevent accidental hammer disengagement from the leads (16-8.ff(1)).
  • Verify stop blocks are installed in the leads to prevent the hammer from being raised against the head block (16-8.ff(10)(d)).
  • Install guards across the top of the head block to prevent the wire rope from jumping out of the sheaves (16-8.ff(12)).
  • Place a blocking device capable of supporting the hammer's weight in the leads under the hammer whenever employees must work under it, except momentary lean-through to guide a pile (16-8.ff(10)(f)).
M
Ground crew struck by the hammer, pile, or debris ejected during driving
  • Keep all personnel except the equipment operator out from under the kicker/spotter and at least 12 feet (or greater if the manufacturer specifies) from the hammer or pile while it is being driven (16-8.ff(6)).
  • Prohibit employees from being on the leads or ladders while a pile is being driven (16-8.ff(10)(b)).
  • Provide the crane/track hoe/forklift operator station with falling object protection (16-8.ff(7)).
  • Keep lead landings clear — store nothing on them (16-8.ff(10)(c)).
M
Whipping of pressurized steam, air, or hydraulic lines on hose or joint failure
  • Securely attach all pneumatic or steam hose connections to hammers, pile ejectors, and jet pipes with at least 1/4-inch alloy steel chain with a 3,250 lb WLL (or wire of equal strength) to prevent whipping if a joint breaks (16-8.ff(13)).
  • Provide two shutoff valves in hydraulic/pneumatic/steam line controls, one a quick-acting lever type within easy reach of the hammer operator (16-8.ff(14)).
  • Perform daily documented inspections covering fuel lines, pressurized hoses, clamps, welds, and hardware before each shift of driving (16-7.e(6)).
L
High-intensity impact noise exposure to operator and ground crew
  • Require hearing protection for all personnel inside the controlled work area, with dual protection (plugs plus muffs) near operating impact hammers per the project hearing conservation program.
  • Position non-essential personnel outside the 12-foot exclusion distance and rotate ground crew to limit exposure duration (16-8.ff(6)).
L
Cutting off driven pile topsCut-off crew struck by an adjacent pile or hammer while driving continues
  • Suspend pile-driving operations during cut-off work unless the cutting operation is located at least twice the length of the longest pile cut-off away from the driver (16-8.ff(17)).
  • Keep cut-off work inside the controlled work area with only directly involved personnel present (16-7.e(7)).
L
Falling or rolling cut-off section striking workers
  • Rig each cut-off section with a positive attachment before completing the cut so the section is lowered under control rather than dropped (16-8.ff(15)(b)).
  • Stage cut-off sections in the designated material storage area, blocked against rolling (16-7.e(2)).
L
Pile extraction (when required)Crane overload or tipover while pulling piling
  • Use a pile extractor if piling cannot be pulled without exceeding the load rating of the equipment (16-8.ff(18)(a)).
  • Equip the crane with an LMI device when pulling piling, unless the load can be determined, is within the crane's load rating chart, and the boom is not raised more than 60 degrees above horizontal; vibratory pulling devices are excepted (16-8.ff(18)(b)).
  • Never pull piling by tipping the crane, momentarily releasing the load brake, and catching the load before the crane settles (16-8.ff(18)(c)).
  • Use a hook with a positive locking safety device when rigging for pile pulling (16-8.ff(18)(d)).
M
Barge-mounted / waterborne pile driving (if applicable)Barge listing, taking on water, or crane breaking loose from its flotation
  • Have a Competent Person inspect the means used to secure the crane to the barge each shift for wear, corrosion, loose or missing fasteners, defective welds, water leaks, and insufficient tension (16-5.i(1)).
  • Have a CP perform the monthly flotation inspection: taking on water, deck load securement, water-tight compartments and hatches, and firefighting and lifesaving equipment in place and functional (16-5.i(2)).
  • Remove the vessel or flotation device from service immediately if a QP determines an identified deficiency constitutes a hazard (16-5.i(3)).
  • Comply with Chapter 19, Floating Plant and Marine Activities, for all work from floating plant (Ch 19).
M
Fall into water / drowning
  • Provide fall protection per Chapter 21 for workers on fixed leads exposed to falls of 6 feet or greater, or any fall over water, machinery, or dangerous operations — guardrails or personal fall protection with certified anchorages (16-8.ff(10)(i)).
  • Provide US Coast Guard-approved PFDs and rescue equipment for personnel working over or adjacent to water per Chapter 19 (Ch 19).
M
Demobilization, disassembly, and cleanupUncontrolled hammer movement while relocating or breaking down the rig
  • Lower the hammer to the bottom of the leads whenever the pile driver is being moved (16-8.ff(15)(d)).
  • Follow the disassembly sequence documented in the site-specific pile driving safety plan (16-7.e(3)).
  • Maintain the controlled work area until leads, hammer, and counterweights are down and secured for transport (16-7.e(7)).
L

Equipment To Be Used

Training Requirements

Inspection Requirements

Competent / Qualified Person Requirements

Applicable EM 385-1-1 (2024) Sections

Applicable OSHA Standards

Need an AHA for a job that's not in the library?

We write a complete, editable Word AHA for your specific job (your "definable feature of work") — EM 385-1-1 (2024) citations, ENG Form 6206 layout, employee sign-off sheet included — delivered by email within 24 hours. $19 per AHA.

Order a Custom AHA — $19 →

How it works: at checkout you fill in a required "Activity / DFOW" field describing your job — that starts the clock. We confirm any details by email and deliver within 24 hours. Need it same-day? Say so in that field — usually possible. If your reviewer doesn't accept the format, we revise it or refund you in full — your call.

See a sample of exactly what you'll receive →

Frequently Asked Questions

What EM 385-1-1 chapter covers pile driving?

In the 2024 edition, pile drivers are load handling equipment under Chapter 16. The pile-specific operating requirements are in para 16-8.ff, the mandatory site-specific safety plan is para 16-7.e, and weekly documented lead inspections are para 16-5.j. Chapter 15 governs the rigging, and Chapter 19 applies when driving from floating plant.

Do I need a site-specific pile driving safety plan in addition to the AHA?

Yes. Para 16-7.e requires a plan before any driving or extraction begins, covering at minimum: utility locations, designated equipment and storage areas, assembly/disassembly sequences, equipment operation and pile handling, a geotechnical report, daily documented equipment inspections, and a controlled work area plan. The AHA and the plan are separate submittals that reviewers will cross-check against each other.

Can we drive piles with an excavator or forklift fitted with a driving attachment?

Yes, but para 16-8.ff(3) requires a Registered Professional Engineer to design any attachment used for other than its intended purpose, and all of 16-8.ff still applies. The RPE must also seal and sign the capacity procedures (16-8.ff(2)(b)), and the operator must be trained and authorized on the attachment (16-8.ff(4)).

What should the overall RAC be for a pile driving AHA?

The overall RAC must not be lower than the highest job step RAC on the AHA (para 2-6.d(4)(f)). With the Chapter 16 controls in place, most pile driving AHAs land at Medium overall, driven by residual struck-by, tipover, and dropped-load exposure during driving and extraction. Submitting an overall Low for this DFOW usually invites reviewer pushback.

How close can workers stand to the pile while it is being driven?

No one except the equipment operator may stand under the kicker/spotter or directly under, in front of, or closer than 12 feet to the hammer or pile during driving — farther if the manufacturer specifies (16-8.ff(6)). Employees are also prohibited from being on the leads or ladders while a pile is being driven (16-8.ff(10)(b)).

Does the 2014 or 2024 edition of EM 385-1-1 apply to my contract?

Solicitations issued on or after 15 March 2024 fall under the 2024 edition cited in this example. Existing contracts stay on the 2014 edition (with its 01.A-style paragraph numbering) until completion. Check your contract's referenced edition before submitting — mixing citation styles is a common reason AHAs get kicked back.