Free EM 385-1-1 (15 Mar 2024) AHA example for site clearing and grubbing: job steps, hazards, controls, residual RACs, in ENG Form 6206 format.
Site clearing and grubbing is usually the first definable feature of work (DFOW) on a USACE or NAVFAC construction contract: felling and removing trees, cutting and chipping brush, ripping out stumps and root mats, and hauling vegetative debris off site before mass grading begins. It concentrates several of the highest-energy hazards on any project into one activity — falling trees, chainsaws, brush chippers, and heavy dozers and excavators working on unimproved terrain — which is why the government approval authority will read this activity hazard analysis closely at the preparatory meeting.
This AHA example is written to EM 385-1-1, 15 March 2024, the current edition for solicitations issued on or after that date; contracts awarded under the 2014 edition stay on the 2014 edition (and its 01.A-style citations) until completion, so confirm which edition your contract invokes before you submit. Per para 2-6, the AHA must be prepared by a Competent Person, list detailed job steps with hazards and controls in hierarchy order, assign a residual Risk Assessment Code (RAC) to each step, carry an overall RAC no lower than the highest step RAC, and be reviewed and signed by every involved employee before work starts.
The download follows the ENG Form 6206 (SEP 2024) layout: the job steps, hazards, controls, and residual RAC table below, plus the equipment, training, and inspection blocks and the employee sign-off sheet. Use it as a starting point for your own activity hazard analysis — edit the steps to match your actual means and methods, your equipment spread, and your named Competent and Qualified Persons before submitting it to the KO or COR.
| Severity ↓ / Probability → | Frequent | Likely | Occasional | Seldom | Unlikely |
|---|---|---|---|---|---|
| Catastrophic | E | E | H | H | M |
| Critical | E | H | H | M | L |
| Moderate | H | M | M | L | L |
| Negligible | M | L | L | L | L |
E = Extremely High Risk · H = High Risk · M = Medium Risk · L = Low Risk (per EM 385-1-1 2024, para 2-2.u/2-2.w and ENG Form 6206). Controls must reduce the residual RAC to a level the approval authority accepts before work proceeds.
On a phone, swipe the table sideways to see the controls and residual RAC columns →
Overall RAC: M — Medium Risk (highest residual step RAC, per EM 385-1-1 2024 para 2-6.d(4)(f))
| Job Step | Hazards | Controls (hierarchy: elimination → engineering → administrative → PPE) | Residual RAC |
|---|---|---|---|
| Mobilization, utility locates, and pre-clearing site survey | Strike on unknown underground utilities (electric, gas, communications, water) while grubbing stumps and ripping root mats |
| M |
| Contact with overhead power lines during tree survey and equipment mobilization |
| M | |
| Exposure to poisonous plants, ticks, and stinging insects during walking survey |
| L | |
| Establish work zone, access control, and staging areas | Unauthorized personnel or public entering the felling and equipment operating area |
| L |
| Slips, trips, and falls on uneven, vegetated, or muddy terrain |
| L | |
| Equipment inspection and setup (dozers, excavators, chipper, chainsaws) | Operating defective or unguarded clearing equipment |
| L |
| Chainsaw or chipper mechanical failure and missing safety devices |
| L | |
| Caught-in equipment during field repairs and adjustments |
| L | |
| Tree felling and removal | Struck by falling tree, limbs, or thrown debris |
| M |
| Chainsaw cuts and kickback |
| L | |
| Electrocution felling trees near energized lines |
| M | |
| Brush cutting and chipping | Caught in brush chipper infeed |
| M |
| Struck by flying chips and ejected material |
| L | |
| Struck by hand-carried brush and hand tool injuries |
| L | |
| Grubbing — stump and root removal with dozer/excavator | Equipment rollover on slopes, stumps, and uneven ground |
| L |
| Operator struck by falling or flying objects (springing roots, thrown stumps, falling snags) |
| L | |
| Underground utility strike while ripping roots and pulling stumps |
| M | |
| Ground personnel struck by reversing equipment |
| L | |
| Loading and hauling debris off site | Workers struck by loaders and dump trucks during loading |
| L |
| Unstable or oversized loads and unsafe dump trucks on haul routes |
| L | |
| Demobilization and site cleanup | Residual brush, logs, and stump holes left as hazards for follow-on trades |
| L |
| Caught-in/struck-by while loading equipment onto transport trailers |
| L |
We write a complete, editable Word AHA for your specific job (your "definable feature of work") — EM 385-1-1 (2024) citations, ENG Form 6206 layout, employee sign-off sheet included — delivered by email within 24 hours. $19 per AHA.
How it works: at checkout you fill in a required "Activity / DFOW" field describing your job — that starts the clock. We confirm any details by email and deliver within 24 hours. Need it same-day? Say so in that field — usually possible. If your reviewer doesn't accept the format, we revise it or refund you in full — your call.
There is no single clearing-and-grubbing chapter — the 2024 manual never even uses the word "grubbing." The activity is governed by a combination of Ch 18 (Vehicles, Machinery, and Mechanized Equipment — including 18-8.b(14) FOPS guards and canopies specifically for equipment used in clearing operations), Ch 31 (Tree Maintenance and Removal, including 31-8.f felling and 31-8.g brush removal and chipping), and Ch 13 (Hand and Power Tools, for chainsaws). OSHA's 1926.604 Site Clearing and 1926.602 apply in parallel.
Solicitations issued on or after 15 March 2024 fall under the 2024 edition; contracts awarded under the 2014 edition remain on that edition until completion. The two editions number requirements completely differently (2024 uses chapter-paragraph cites like 31-8.g; 2014 used cites like 01.A.14), so check your contract before copying citations. This example is written to the 2024 edition.
Yes, if your clearing involves tree maintenance or removal — which almost all clearing does. Para 31-7 requires a plan developed by or under the direction of a Qualified Tree Worker covering the activity description, tree sizes and fall directions, anticipated hazards, personnel assignments, a retreat path, and access control, submitted for USACE approval or KO/COR acceptance before work. The AHA does not substitute for it.
The overall RAC must not be lower than the highest residual step RAC (2-6.d(4)(f)). With the controls in this example, tree felling near structures or power lines, chipper operations, and utility strikes during grubbing typically remain Medium after controls, so most clearing and grubbing AHAs carry an overall residual RAC of M. Remember the 2024 severity scale is Catastrophic/Critical/Moderate/Negligible — "Marginal" is 2014 language.
Cutting brush at grade may not disturb soil, but grubbing does — stump pulling and root ripping penetrate well below grade. Para 25-8.f requires a dig permit, utility company locates and markings, and physical verification by non-destructive means when working within 3 ft of a marked utility, before that mechanical work starts. Treat the grubbing phase like any other excavation for locate purposes.
The Competent Person who prepared it, the approval authority who accepts it before work begins (2-6.c(1)), and every employee involved in the activity, who must review and sign it before starting work (2-6.d(2)). New crew members sign before they join the work, and the AHA stays on site for 12 months or the life of the contract (2-6.d(3)).