EM 385 AHA Library

Rebar & Formwork Installation AHA Example (EM 385-1-1)

Free EM 385-1-1 (2024) AHA example for rebar and formwork installation: job steps, hazards, controls, residual RACs, and citations for USACE/NAVFAC work.

Download Word Sample (free) Download PDF Sample (free)
Free download, no email required. Adapt every step, hazard and control to your site's actual conditions before your SSHO signs it.
On a phone? Tap the PDF to view it, then use the share icon to text or email it — the Word file is best opened on a computer.

Rebar and formwork installation is the definable feature of work (DFOW) that precedes every cast-in-place concrete placement: staging and tying reinforcing steel, erecting and bracing formwork and shoring, supporting the pour, and stripping and reshoring afterward. On USACE and NAVFAC contracts this work falls under EM 385-1-1 (15 March 2024) Chapter 27, Concrete, Masonry, Roofing, and Wood Construction, with fall protection under Chapter 21 and material handling and storage under Chapter 14. The controlling failure modes are well known: formwork and shoring collapse during or after the pour, impalement on protruding rebar, and premature stripping before the concrete has gained sufficient strength.

This activity hazard analysis (AHA) example is written for SSHOs, superintendents, and project engineers who need to prepare or review an AHA before the preparatory phase meeting on a federal job. It follows the ENG Form 6206 (SEP 2024) structure: sequenced job steps, the hazards of each step, controls ordered by the hierarchy in para 2-6.b, a residual Risk Assessment Code (RAC) per step, and the equipment, training, and inspection requirements with the Competent Person and Qualified Person designations Chapter 27 actually requires. Note that beyond the AHA itself, para 27-7.a requires a QP-developed erection and removal plan for all formwork other than slab on grade.

Citations below are to the 2024 edition in chapter-paragraph format (for example, para 27-8.e(10)); contracts solicited before 15 March 2024 typically remain on the 2014 edition, which uses different section numbering, so confirm which edition your contract invokes before copying citations. Use this AHA example as a verified starting point, then edit the steps, equipment, and named CP/QP designations to match your site, your formwork system, and your crew.

Risk Assessment Code (RAC) Matrix — EM 385-1-1 (2024)

Severity ↓ / Probability →FrequentLikelyOccasionalSeldomUnlikely
CatastrophicEEHHM
CriticalEHHML
ModerateHMMLL
NegligibleMLLLL

E = Extremely High Risk · H = High Risk · M = Medium Risk · L = Low Risk (per EM 385-1-1 2024, para 2-2.u/2-2.w and ENG Form 6206). Controls must reduce the residual RAC to a level the approval authority accepts before work proceeds.

Sample AHA: Rebar and Formwork Installation

On a phone, swipe the table sideways to see the controls and residual RAC columns →

Overall RAC: M — Medium Risk (highest residual step RAC, per EM 385-1-1 2024 para 2-6.d(4)(f))

Job StepHazardsControls (hierarchy: elimination → engineering → administrative → PPE)Residual RAC
Mobilization, material delivery, and staging of rebar and form materialsStruck-by or crushed-by during offloading of rebar bundles and form panels
  • Establish an exclusion zone around the offloading area and keep all non-essential personnel clear of suspended loads; no one works under bundled material loads (27-8.a(4)(a)).
  • Use tag lines to control rebar bundles and form panels during hoisting, and rig loads under the direction of a qualified rigger (Ch 15).
  • Unload cylindrical and bundled material using a method that keeps workers off the unloading side of the carrier after tie wires are cut (14-8.b(20)(d)).
L
Trip, laceration, and toppling hazards from disorderly material storage
  • Store reinforcing steel in orderly piles located away from walkways and roadways (14-8.b(19)(a)).
  • Stack and block form lumber and cylindrical materials to prevent spreading, tilting, or sliding, and securely pile steel so members cannot slide off (14-8.b(19)–(20)).
  • Follow the material delivery, storage, and staging procedures in the QP's formwork erection and removal plan (27-7.a(3)).
L
Manual handling injuries (strains, pinch points) moving rebar and panels
  • Use mechanical means (forklift, crane, buggies) for bundles and panels instead of manual carrying wherever the site layout allows.
  • Assign team lifts for long bar and awkward panels and pre-plan carry routes to keep them clear of debris and grade changes.
  • Wear cut-resistant gloves, safety-toe boots, hard hats, and eye protection selected for the task per Ch 5 (27-8.a(5)).
L
Pre-work planning: formwork/shoring design verification and plan reviewShoring erected to an unverified or deviated design, leading to later collapse
  • Obtain the QP-developed erection and removal plan required for all formwork other than slab on grade, and confirm it is accepted by the KO/COR before work begins (27-7.a).
  • Have an RPE qualified in structural design inspect shoring equipment prior to erection to verify it matches the shoring design, and remove damaged equipment from service (27-5.a(1)).
  • Keep the fabricated shoring system manufacturer's specifications on site during planning and execution, and do not exceed the manufacturer's safe working load (27-8.e(3), 27-8.e(5)(g)).
  • Design and plan formwork and shoring according to ACI 347R-14 (27-8.e(1), 27-1.a).
L
Crew unaware of sequence, hazards, or stop-work triggers
  • Review this AHA at the preparatory meeting; every involved employee reviews and signs it before starting work (2-6.d(2)).
  • Designate in writing, by name, the CP for formwork/shoring, the QP who prepared the plan, and the CP for fall protection (2-6.d(4)(g)).
  • Update the AHA when site conditions or the shoring system change, and resubmit if the RAC increases (2-6.d(5)(a)).
L
Erect and brace formwork and shoringFormwork/shoring collapse during erection from inadequate base support or bracing
  • Verify supporting ground or completed construction has adequate strength for the applied vertical and lateral loads, and that sills are sound, rigid, and capable of carrying the maximum intended load (27-8.e(5)(a)-(b)).
  • Keep base plates, shore heads, extension devices, and adjustment screws in firm contact with the footing sill and form material, secured where necessary (27-8.e(5)(c)).
  • Provide diagonal bracing in vertical and horizontal planes, and brace single post shores in both longitudinal and transverse directions, installing bracing as the shores are erected (27-8.e(5)(e), 27-8.e(6)(f), 27-8.e(6)(f-3)).
  • Reject fabricated single post shores or adjusting devices that are heavily rusted, bent, dented, re-welded, or have broken welds, and timber that is split, cut, or rotted (27-8.e(4)).
  • Have a structural engineer design and inspect the layout wherever single post shores are used in more than one tier (27-5.a(3), 27-8.e(6)(a)).
M
Falls from elevation while setting wall forms and deck formwork
  • Provide fall protection at 6 feet (1.8 m) for all Chapter 27 work using guardrails, work platforms, or personal fall protection systems (27-8.a(1), Ch 21).
  • Have the CP for fall protection select the system, and ensure Authorized Persons are trained by a CP before using personal fall protection equipment (21-4.c, 21-3.d).
  • Inspect personal fall protection equipment before each use and remove from service anything damaged or subjected to a fall (21-5.a).
L
Struck-by and pinch-point injuries handling panels and shore frames
  • Verify all locking devices on frames and braces are in good working order, coupling pins align frame legs, and pivoted cross braces have their center pivot in place before assembly (27-8.e(8)(a)).
  • Secure posts located near the slab perimeter during assembly to prevent post fall-out (27-8.e(6)(f-4)).
  • Keep hands clear of closing surfaces when landing panels; use tag lines on hoisted forms.
L
Install and tie reinforcing steelImpalement on protruding rebar and fasteners
  • Guard all protruding reinforcing steel onto which workers could fall with impalement protection (OSHA-compliant rebar caps or troughs) before exposure is created; do not allow employees to work above or in positions exposed to impalement hazards until the hazard is controlled (27-8.a(3), 1926.701(b)).
  • Provide fall protection regardless of height wherever a fall onto an impalement hazard is possible (21-8.a(3)(a)).
  • Inspect impalement protection daily and replace displaced or damaged caps immediately.
L
Collapse of vertical rebar assemblies (walls, piers, columns)
  • Brace, guy, weld, or otherwise support reinforcing steel for walls, piers, columns, and similar vertical structures to prevent overturning or collapse (27-8.c(1)).
  • Use an RPE-designed support system for any reinforcing steel supports that are independent of other shoring support systems (27-8.c(1)).
  • Secure turnbuckles against unwinding under stress and place plumbing-up guys so workers can reach connection points; the CP oversees removal of plumb-up guys (27-8.c(2)-(4), 27-4.a(1)).
M
Wire mesh recoil and tie-wire lacerations
  • Secure unrolled wire mesh to prevent recoiling before cutting bands (27-8.c(5)).
  • Wear cut-resistant gloves and eye protection for tying and cutting operations (Ch 5).
  • Turn tie-wire tails down or cap them where they create snag or laceration exposure on walking/working surfaces.
L
Falls while working from rebar mats and formwork at elevation
  • Provide guardrails, work platforms, or personal fall protection at 6 feet and above; formwork and rebar assembly are listed fall-protection exposures (27-8.a(1), 21-8.a(3)(b)).
  • Have the CP for fall protection verify anchorage and system selection for workers tying steel above the 6-foot threshold (21-4.c).
  • Maintain clear access routes onto the mat and prohibit climbing formwork bracing as access.
L
Pre-pour inspection and support during concrete placementShoring failure under fluid concrete load during the pour
  • Inspect erected shoring equipment immediately prior to, during, and immediately after concrete placement; immediately reinforce or re-shore any shoring found damaged, displaced, or weakened (27-5.a(2)).
  • Place concrete following the sequence and rate assumed in the approved formwork design so lateral pressures are not exceeded (27-8.e(2), 27-7.a).
  • Do not adjust single post shores to raise formwork after concrete is in place (27-8.e(6)(d)).
  • Do not place construction loads on the structure unless a person qualified in structural design confirms it can support them (27-8.a(2)).
M
Struck-by from concrete buckets and pump discharge lines
  • Keep all employees, including vibrator crews, out from under concrete buckets and other suspended loads, and route elevated buckets to minimize worker exposure (27-8.a(4)).
  • Verify bucket gates have positive safety latches to prevent accidental dumping (27-8.b(1)(e)).
  • Support pump discharge pipes on supports designed for 100% overload and secure tremie sections with wire rope in addition to couplings (27-8.b(1)(f), 27-8.b(1)(h)).
L
Strip formwork and shoring; install reshoresStructural collapse from premature formwork or shoring removal
  • Do not remove forms or shores (except slab on grade and slip forms) until the CP for forming/shoring determines the concrete has gained sufficient strength to support its weight and all superimposed loads (27-8.e(10), 27-4.a(2)).
  • Base the CP's determination on the plans-and-specifications removal conditions or on concrete testing, per the strength-determination procedures in the erection and removal plan (27-8.e(10)(a)-(b), 27-7.a(4)).
  • Provide reshoring to safely support slabs and beams after stripping or where members carry superimposed construction loads (27-8.e(5)(f)).
  • Follow the removal sequence in the QP's erection and removal plan (27-7.a(1)).
M
Struck-by falling panels and shores during stripping
  • Establish a controlled access zone below and around the stripping operation and keep other trades out until stripped material is landed and stacked.
  • Secure perimeter posts during dismantling and reshoring to prevent post fall-out (27-8.e(6)(f-4)).
  • Lower panels and shores in a controlled manner; do not drop them to the deck or ground.
L
Puncture wounds and impalement from protruding nails in stripped lumber
  • Pull or bend over protruding nails as lumber is stripped and before stacking; do not allow work in positions exposed to protruding fasteners until controlled (27-8.a(3)).
  • Stack stripped material in orderly piles away from walkways as it is generated (14-8.b).
  • Wear puncture-resistant footwear and gloves per the PPE assessment (Ch 5).
L
Demobilization, housekeeping, and material disposalTrips, lacerations, and public exposure from accumulated debris and stored material
  • Remove form debris and cut rebar from work areas daily and dispose of material per the site plan (14-8.c).
  • Restack reusable shores, panels, and remaining rebar in orderly, blocked piles clear of walkways and roadways (14-8.b(19)-(20)).
  • Where the work presents a hazard to the public, maintain barricades and postings per MUTCD and ANSI/ASSP A10.34 until the area is cleared (27-8.a(6)).
L
Struck-by during load-out of stripped materials
  • Rig and hoist banded loads of stripped panels and shores with tag lines and an exclusion zone; no workers under suspended loads (27-8.a(4)(a)).
  • Verify banding and pallet integrity before hoisting stripped material that may contain loose pieces.
L

Equipment To Be Used

Training Requirements

Inspection Requirements

Competent / Qualified Person Requirements

Applicable EM 385-1-1 (2024) Sections

Applicable OSHA Standards

Need an AHA for a job that's not in the library?

We write a complete, editable Word AHA for your specific job (your "definable feature of work") — EM 385-1-1 (2024) citations, ENG Form 6206 layout, employee sign-off sheet included — delivered by email within 24 hours. $19 per AHA.

Order a Custom AHA — $19 →

How it works: at checkout you fill in a required "Activity / DFOW" field describing your job — that starts the clock. We confirm any details by email and deliver within 24 hours. Need it same-day? Say so in that field — usually possible. If your reviewer doesn't accept the format, we revise it or refund you in full — your call.

See a sample of exactly what you'll receive →

Frequently Asked Questions

What EM 385-1-1 chapter covers rebar and formwork installation?

Chapter 27, Concrete, Masonry, Roofing, and Wood Construction, in the 15 March 2024 edition. Formwork and shoring inspections are at para 27-5.a, the erection and removal plan at 27-7.a, reinforcing steel at 27-8.c, and formwork/shoring design and removal at 27-8.e. Fall protection is Chapter 21 and material storage is Chapter 14.

Do I need a formwork erection and removal plan in addition to the AHA?

Yes. Para 27-7.a requires a QP-developed erection and removal plan for all formwork other than slab on grade, submitted to the USACE supervisor for approval or to the KO/COR for acceptance. The plan must cover the erection and removal sequence, hazards and controls, material staging, strength-determination procedures for stripping, named QPs/CPs, and inspection methods. The AHA does not replace it.

When can we strip forms and shores?

Only after the CP for forming or shoring determines the concrete has gained sufficient strength to support its own weight and all superimposed loads (para 27-8.e(10)). The determination must be based either on the removal conditions in the plans and specifications or on concrete testing. Slab-on-grade forms and slip forms are the only exceptions, and reshoring must be provided where stripped members carry construction loads.

What impalement protection is required for protruding rebar?

Para 27-8.a(3) prohibits employees from working above or in positions exposed to protruding reinforcing steel or other impalement hazards until provisions control the hazard — in practice, OSHA-compliant rebar caps or troughs per 29 CFR 1926.701(b). Para 21-8.a(3)(a) additionally requires fall protection regardless of height wherever a worker could fall onto an impalement hazard.

What should the overall RAC be for rebar and formwork work?

The overall RAC must not be lower than the highest job step RAC on the AHA (para 2-6.d(4)(f)). For this activity that is typically M (Medium), driven by formwork/shoring collapse during erection and placement and by premature stripping, which remain Moderate-to-Critical severity events even with controls in place. Note the 2024 severity scale uses "Moderate," not the 2014 term "Marginal."

Does the 2014 or 2024 edition of EM 385-1-1 apply to my contract?

Solicitations issued on or after 15 March 2024 fall under the 2024 edition; existing contracts generally remain on the 2014 edition until completion. The two editions number requirements differently (2024 uses chapter-paragraph cites like 27-8.e; 2014 used cites like 01.A.14), so verify which edition your contract invokes before citing paragraphs in your AHA.

Related Sample AHAs