HVAC installation activity hazard analysis (AHA) example for EM 385-1-1 (2024): job steps, hazards, controls, and RACs for USACE and NAVFAC contractors.
HVAC and mechanical equipment installation is a definable feature of work (DFOW) on nearly every federal vertical construction project: setting air handlers, RTUs, chillers, and condensing units; hanging ductwork; brazing refrigerant piping; running hydronic lines; making electrical tie-ins; and pressure testing the completed systems. There is no single dedicated chapter in EM 385-1-1 for HVAC work — this activity hazard analysis is a composite that pulls its requirements from Chapter 14 (material handling), Chapter 16 (load handling equipment), Chapter 10 (welding, cutting, and brazing), Chapters 11 and 12 (electrical work and control of hazardous energy), Chapter 20 (pressurized equipment and systems), Chapters 21, 22, and 24 (fall protection, work platforms, and safe access), and Chapter 34 (confined space entry for plenums and mechanical pits).
This AHA example is written for mechanical contractors and their SSHOs working on USACE and NAVFAC projects, where an accepted AHA is required before work begins on each activity (para 2-6.c(1)) and every involved employee must review and sign it (para 2-6.d(2)). The page walks through a realistic eight-step installation sequence with the hazards, controls written to the hierarchy in para 2-6.b (elimination through PPE), and residual Risk Assessment Codes for each step, plus the equipment, training, inspection, and competent person entries the ENG Form 6206 format calls for. One trap specific to this DFOW: para 20-8.e(3) requires a supplemental preparatory meeting to re-review the test procedures and AHA when pressure testing occurs two or more months after the initial piping preparatory meeting — a gap that is almost guaranteed on an HVAC scope.
All citations on this page use the EM 385-1-1, 15 March 2024 edition (chapter-paragraph format, e.g., 20-8.e(3)); contracts solicited before 15 March 2024 generally remain on the 2014 edition with its old section-style numbering (e.g., 01.A.14) until completion, so verify which edition your contract invokes before copying any AHA example.
| Severity ↓ / Probability → | Frequent | Likely | Occasional | Seldom | Unlikely |
|---|---|---|---|---|---|
| Catastrophic | E | E | H | H | M |
| Critical | E | H | H | M | L |
| Moderate | H | M | M | L | L |
| Negligible | M | L | L | L | L |
E = Extremely High Risk · H = High Risk · M = Medium Risk · L = Low Risk (per EM 385-1-1 2024, para 2-2.u/2-2.w and ENG Form 6206). Controls must reduce the residual RAC to a level the approval authority accepts before work proceeds.
On a phone, swipe the table sideways to see the controls and residual RAC columns →
Overall RAC: M — Medium Risk (highest residual step RAC, per EM 385-1-1 2024 para 2-6.d(4)(f))
| Job Step | Hazards | Controls (hierarchy: elimination → engineering → administrative → PPE) | Residual RAC |
|---|---|---|---|
| Mobilization, equipment delivery, offloading, and staging of HVAC units and materials | Struck-by or crushed-by during forklift/telehandler offloading of AHUs, RTUs, and duct bundles |
| L |
| Back and shoulder strains from manually handling duct sections, VAV boxes, and pipe |
| L | |
| Collapse of stacked materials or failure of storage racking in the laydown area |
| L | |
| Crane and hoist operations — setting RTUs, chillers, and AHUs on roofs and pads | Dropped or shifted load from rigging failure or improper hitch during equipment picks |
| M |
| Workers struck by the swinging load or caught in the swing radius |
| M | |
| Crane contact with overhead power lines or rooftop obstructions |
| L | |
| Installing ductwork, piping, and equipment at height from MEWPs, scaffolds, and ladders | Falls of 6 ft or more from MEWPs, scaffolds, mezzanines, roof edges, and floor openings |
| M |
| Scaffold collapse or ejection from an incomplete or defective scaffold |
| L | |
| Falls from damaged or misused ladders during hanger and trim work |
| L | |
| Brazing, soldering, and welding of refrigerant and hydronic piping (hot work) | Fire ignition of combustible construction materials by brazing flame, sparks, or slag |
| L |
| Toxic fume and oxygen-displacement exposure when brazing in mechanical rooms or shafts |
| L | |
| Compressed gas cylinder fire or violent release (oxy-fuel and nitrogen cylinders) |
| L | |
| Electrical rough-in and equipment tie-ins to building power | Shock or arc flash from unexpected energization while connecting units, VFDs, and disconnects |
| M |
| Shock from damaged cords and temporary power feeding drills, threaders, and vacuum pumps |
| L | |
| Work inside air plenums, ducts, crawl spaces, and mechanical pits | Hazardous atmosphere or engulfment/entrapment in confined spaces (plenums, large ducts, pits) |
| M |
| Contact with unidentified in-duct hazards (energized heaters, rotating dampers/fans) during interior duct work |
| L | |
| Pressure testing of refrigerant piping and hydronic systems | Violent release of stored energy — fitting blow-off, pipe whip, or projectile failure during pneumatic testing |
| M |
| Failure of regulators, hoses, or gauges on nitrogen test rigs |
| L | |
| System startup, refrigerant charging, commissioning, and demobilization | Refrigerant release causing frostbite injury or oxygen displacement in mechanical rooms |
| L |
| Contact with rotating fans, belts, and drives during commissioning checks |
| L | |
| Slips, trips, and lacerations during cleanup and demobilization |
| L |
We write a complete, editable Word AHA for your specific job (your "definable feature of work") — EM 385-1-1 (2024) citations, ENG Form 6206 layout, employee sign-off sheet included — delivered by email within 24 hours. $19 per AHA.
How it works: at checkout you fill in a required "Activity / DFOW" field describing your job — that starts the clock. We confirm any details by email and deliver within 24 hours. Need it same-day? Say so in that field — usually possible. If your reviewer doesn't accept the format, we revise it or refund you in full — your call.
There is no dedicated HVAC chapter in the 2024 edition. HVAC installation is a composite activity: Ch 14 governs material handling and storage, Ch 16 the crane and hoist picks, Ch 10 brazing and welding hot work, Chs 11 and 12 the electrical tie-ins and energy isolation, Ch 20 pressure testing, Chs 21/22/24 work at height and access, and Ch 34 any plenum or pit that meets the confined space definition. Your AHA should cite the specific paragraphs from each chapter that apply to your scope.
Pressure testing belongs in the HVAC AHA, but Ch 20 adds two gates: a CP must develop the test procedures and submit them to the KO or COR for acceptance (20-8.e(2)), and if acceptance testing happens two or more months after the initial piping preparatory meeting, you must hold a supplemental preparatory meeting to re-review the test procedures and the AHA before testing (20-8.e(3)). Pneumatic testing is only allowed where the manufacturer's specifications or an applicable code permit it (20-8.e(1)).
Yes — hot work permits are required on federal installations when hot work is performed, unless the USACE supervisor/KO or COR indicates otherwise (10-8.d(2)). The AHA must also identify the CP for welding and the fire watch, and the fire watch must remain in place a minimum of 30 minutes after the exposure ends (10-6.d).
It can be. Evaluate each plenum, duct section, crawl space, and mechanical pit against the Ch 34 confined space criteria before entry. If a space is permit-required, the Entry Supervisor must develop a written Site-Specific Confined Space Plan and submit it for acceptance before work begins (34-7.b), and each entry needs an AHA identifying all existing and potential hazards (34-6.a).
The overall RAC must not be lower than the highest job step RAC on the AHA (para 2-6.d(4)(f)). For a typical HVAC installation with crane picks, work at height, energized tie-ins, and pneumatic testing, several steps reasonably carry a residual M even after controls, so the overall RAC is usually Medium. An overall L would suggest the hoisting, fall, and stored-energy hazards were underrated.
Solicitations issued on or after 15 March 2024 fall under the 2024 edition; existing contracts generally remain on the 2014 edition until completion. The two editions use completely different numbering — the 2024 manual cites chapter-paragraph (e.g., 20-8.e), while 2014 used section style (e.g., 01.A.14) — so confirm the edition in your contract before reusing citations from any AHA example.